June 8th 2015 - After exactly one year, the all new Roberts Honda is open for business!!
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
May 6th 2015 - Grading complete and blacktop is down. Lots of work going on inside. We're getting close now.....
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
April 24th 2015 - Not too much difference on the outside but the inside is looking great. Just a few more weeks.......
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
March 23rd 2015 - All the signs are now up and lot grading has started. The interior is painted and tiled floors are being installed.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
March 10th 2015 - Exterior painting complete and the first sign is now up on the building!
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
January 9th 2015 - All the glass is now in place, high speed garage doors installed and the heating system has been fired up. A lot of work going on inside now to keep us on track for a spring opening.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
-
December 12th 2014 - Exterior weatherproofing has been appiled (no, the building will not be yellow when it's finished).
Glass is being installed this week and heating/AC is being installed inside.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
November 25th 2014 - Not too much difference externally but framework for the
 windows is being installed and interior framing taking shape. Snow, snow, stay away!
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

October 17th - The block walls for the service drive-through are up and the
framework for the showroom entrance and delivery canopy is taking shape.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

September 19th 2014 - The steel framework is starting to take shape.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
September 10th 2014 - The concrete pad is poured, levelled and dried by the end of the day. Next comes the steel framework. Â
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

September 10th 2014 - The concrete trucks are here!
--------------------------------------------------------------------------------------------------------------------------------------------------------

August 15th 2014 - The past 6-7 weeks has seen the footers dug and concrete poured. The 2 new stairwells are up and tons of stone has been compressed to raise the floor up approximately 18 inches higher than the previous level.
--------------------------------------------------------------------------------------------------------------------------------------------------------

June 23rd 2014 - The old building has gone and new construction can begin.
--------------------------------------------------------------------------------------------------------------------------------------------------------

June 18th 2014 - Still demolishing.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

June 9th 2014 - Making good progress.
--------------------------------------------------------------------------------------------------------------------------------------------------------

May 30th, 2014 - The wrecking machine has moved in. This is after the first 3 days. These guys are good!
 ![]() |  ![]() |
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

May 2014 - This will be the home of our Honda franchise in Summer of 2015. Until then, Goodbye Old Friend!